
SEI
Jetty: Final Report
Little Bay Emergency Jetty, Montserrat, West Indies Marine Monitoring and Mitigation Final Report Executive
Summary
This is the final report on monitoring and mitigation for the Little
Bay Jetty in Montserrat. The report describes the nature and extent of the
impacts of jetty construction on marine life in the bay. Observed changes
in marine life are evaluated in relation to jetty construction and to island-wide
ecological processes and patterns. For these latter comparisons, we provided
the Institutes own data from previous and ongoing work in Montserrat.
The results or this project are discussed and evaluated in light of the
predictions and recommendations of the Environmental Impact Assessment (EIA).
This project reflects the efforts of a broad diversity of individuals
and groups that began prior to the EIA in 1996. During the EIA process,
SEI scientists concluded that the original design and location were unacceptable
from an environmental perspective. L. G. Mouchel prepared a new design,
and a new location was identified for the jetty to balance environmental
concerns and construction requirements. Through the work of SEI scientists,
L.G. Mouchel engineers (R. Trevitt), the EMAD/ODA, the Montserrat Environmental
Review Panel, the Physical Planning Unit, and the input of private and concerned
citizens, a compromise solution was reached. As part of that solution, a
monitoring and mitigation program was put forth in the EIA. The ODA, Physical
Planning Unit, and L. G. Mouchel agreed in a Memorandum of Agreement to
proceed with the jetty, and to include a marine monitoring and mitigation
component. The work was carried out independently by SEI scientists, and
by local personnel hired and trained by SEI.
This report documents the results of the monitoring and mitigation efforts.
The project lasted from late December 1996 through March 1997 and provided
a scientific assessment of construction impacts. Our only disappointment
is that the monitoring effort was not funded through completion of the entire
jetty. This represents a lost opportunity. Much time, effort, and funding
was invested in getting such a unique project to this stage. The results
to date provide valuable information for all sectors of the community and
they can be used in decision making for future projects and proposed developments.
This was a unique project and we are unaware of any other similar work.
The project successfully provided accurate and scientific information from
an independent group, and was effective in training local personnel. Its
early completion is a loss.
Monitoring and Mitigation centered around minimizing impacts to the marine
life in Little Bay. The program was designed by SEI scientists, and approved
by ODA and Montserrat and included the following components:
- Transplanting corals at risk of mortality from habitat destruction
and sedimentation from the construction zone to a safe zone, and subsequently
monitoring the effectiveness of the relocation.
- Monitoring sediment input and its effect on the health of the marine
life, and making appropriate recommendations when impacts were detected
- Monitoring the extent and severity of the construction impacts on the
marine life (corals and other sessile species, fish, and invertebrates),
providing an early warning when impacts were detected, and suggesting possible
solutions.
- Training of local personnel in scientific monitoring of marine resources
This report describes and evaluates the results of these components.
During the monitoring and mitigation phase, all interested personnel were
kept informed by weekly reports, and monthly summaries of results. These
written reports were distributed to L. G. Mouchel, ODA, Physical Planning
Unit, Department of Fisheries, and the Montserrat National Trust. Updates
were posted on the SEI web site (http://www.sei.org).
Little Bay is located in the north coast of Montserrat and bounded by
Rendezvous Bluff on the north and Potato Hill on the south end (Figure 1.1a).
The emergency jetty currently under construction is located in the North-Central
section of the bay. The coral reefs are located along the bluff, and monitoring
and mitigation work in Little Bay was concentrated on the coral reefs. For
analysis of impacts, the reef section was divided into 4 Areas (A, B, C,
and D) from east to west (Figure 1.2b). Area A was closest to the jetty
location. Monitoring and mitigation began at the end of December 1996 and
continued through March 1997. During that time, Phase 1 of the jetty was
completed (Figure 1.2a,b).
Coral Transplant Mitigation: Recognizing that certain corals close
to the construction (Area A) were at risk of mortality from jetty construction,
scientists recommended transplanting them to a safe zone at the western
edge of Rendezvous Bluff. Transplanting was carried out according to SEI
procedures. Criteria for transplanting included: susceptibility to mortality
from construction; size/age of species; importance of the species to the
biological community; recruitment rates; and probability of success in transplanting.
Based on these criteria, 30 corals and sponges were tagged, measured, photographed
and transplanted from the construction zone to a new location off the western
edge of Rendezvous Bluff. A further 32 corals were designated controls and
these were tagged, measured, and were not-transplanted. An additional 10
corals were transplanted to the same area, as transplant controls (The latter
tested the effect of the transplant process on corals).
At the time of writing, all transplanted species are alive and healthy.
Within a day of transplanting all species were feeding and within a month
fish had taken up residence in some of the corals. Control corals in Areas
B and C ( west of the jetty construction site) were also healthy. By contrast
corals in Area A (close to the jetty) and sponges had disintegrated and
were bleached, indicating that construction had a negative effect on coral
life. Transplanting successfully increased the probability of survival and
reproduction for those individuals relocated to a new habitat.
The importance of ensuring the survival of transplanted species must
be appreciated, particularly in the context of the marine ecosystem. Corals
recruit sporadically to Montserrat (Brosnan et al 1996) and many grow slowly
(often only 2-5cm per year). They provide a habitat for a diversity of species
and form the base of the food chain on a coral reef. Coral loss can lead
to reductions in grazers and carnivorous fish directly, and indirectly through
effects on the food chain. Transplanting, by increasing the survival of
relocated corals and sponges minimized the negative effects of the jetty
on the marine ecosystem, and on the human communities that depend on coral
reefs for food.
Sedimentation and Other Physical Factors: Sediments kill corals,
and increased sedimentation is cited as a key factor in the global decline
of coral reefs. Sediments kill marine organisms by smothering them, and
by reducing light levels so that photosynthesis is inhibited or reduced.
In this program, we monitored changes in sediment load at Little Bay using
sediment traps, by measuring sediment directly on the substrate, and by
secchi disk measurements. (Secchi disks are used to record water clarity.)
Sediments naturally enter the ocean from land (mainly through ghauts)
and by movement and re-deposition of marine sediments. In Montserrat, the
volcano contributes another source of sedimentation. At Little bay, construction
impacts provided an additional source of sediments. At issue is whether
this additional source exceeded the normal levels and induced stress in
the marine community. It can be difficult to distinguish among different
sources, especially during heavy swells. In this study, data from all "designated
Areas" of the bay (A-D), and comparisons with data from other sites
provided ways to distinguish among sources and effects.
Sediment load increased and water clarity significantly decreased at
Little Bay in response to jetty construction. Sediment levels were consistently
higher at Little Bay in comparison to Garibaldi Bluff (known to be impacted
by volcanic runoff) and at Rendezvous Bay. Most changes were confined to
Area A (close to the jetty) but on occasions sediment plumes extended the
length of the Rendezvous bluff. In mid-January average sediment depth in
Area A at Little Bay was 4.74cm. In addition parts of the area were accumulating
sediment at the rate of 15.13 grams per day. At the same time sediment depth
at Garibaldi Bluff was on average 0.5cm. Increased sedimentation was associated
with the use of a fine cement in January. In response to the environmental
concerns raised by SEI, the engineering consulting firm L. G. Mouchel and
Partners and Edgehill Contractors switched to a coarser cement that tended
to settle in the construction blocks. This alleviated much of the problem.
Water clarity at all sites increased significantly with distance from shore,
indicating that sediment settles out relatively quickly. The sediment data
form the basis for interpreting much of the biological changes as most of
the impacts on the reef ecosystems appear to be due to increased sedimentation
and habitat destruction.
Although not within the monitoring and mitigation work, it is important
to address the changes to the ghaut at Little Bay insofar as it affects
marine processes. Ghauts are a main source of sediment into the marine environment.
They also carry nutrients which can lead to the replacement of corals by
algae, with an accompanying loss of reef area and function. Changes made
to the ghaut at Little Bay (through vegetation removal and modifications)
have resulted in increased water flow through the ghaut. This is likely
to increase the rate of erosion, and to increase sediment load into the
sea. Note that prior to construction, most water percolated through the
soil and only rarely flowed through the ghaut. On those occasions when water
flowed through the ghaut its velocity was less that currently observed (T.
Grubba personal observation). We raise this as an issue of future
concern as impacts are likely to be gradual and cumulative.
Jetty Impacts on Corals and Other Sessile Organisms (photoquadrat
analysis): A series of photoquadrats were established to monitor the
impacts of construction on sessile (attached) species including corals,
sponges and algae, and to monitor changes in sediment cover. Quadrats were
photographed and images scanned into a computer and analyzed for percent
cover. Data were subsequently analyzed by Analysis of Variance technique
(ANOVA). Comparisons were made between results from the EIA (Little Bay
1996) and Little Bay 1997. Data from our ongoing work (1995-1997) at other
sites in Montserrat served as control sites for interpreting changes within
Little Bay in comparison to island-wide patterns.
The main results of the photoquadrat analysis showed degradation of corals
and sponges in the area close to jetty construction (Area A). These impacts
included disintegration of sponges and coral bleaching. These phenomena
were not observed elsewhere within the bay or at other sites, indicating
that construction negatively impacted marine life, and that impacts were
localized. Corals showed a downward trend in abundance in Area A, but not
elsewhere, suggesting that construction was the causal factor (Figures 4.2-4.4).
Algal cover (Dictyota species) almost doubled in Area A, but there
was an island-wide increase in algae and so results cannot be attributed
only to jetty construction (Figures 4.2-4.4). Sediment increased in Little
Bay both in cover and depth. We cannot fully evaluate the long-term impacts
of the jetty construction as the process is ongoing, and changes in slow
growing species cannot be observed in a short (3 month) period. Long-term
changes, if any, can only be detected by further monitoring.
Construction Impacts on Fish Life: The effect of jetty construction
on fish life was monitored using a series of 20m transects in Little Bay
and at control sites (Rendezvous Bay and Garibaldi Bay). Jetty construction
led to a decrease in fish life throughout the bay between January and February
19, 1997. This corresponded to a period of high turbidity resulting from
the use of fine sediments in the construction. When conditions cleared in
late February 1997, the abundance and diversity of fish rebounded. Some
fish, e.g. grunt species, which were present in Area A prior to construction,
disappeared from this area and were not observed during the monitoring work.
Chromis and juvenile wrasse increased at Little Bay and at other sites in
February and March. Towards the end of the monitoring study we began to
observe further recruitment of a diverse range of fish species in Areas
B-D of Little Bay. This indicates that the site remains an important recruitment
site for fish. It further illustrates the importance of relocating the jetty
to a more southerly site in the bay and preserving the reefs for key juvenile
species in Areas B-D.
Construction impacts on invertebrates: The abundance and diversity
of invertebrates was recorded by visual transects. Transects were carried
out at Little Bay (Areas A-D), Garibaldi Bluff and Rendezvous Bay. T-test
analyses were used to test for differences among sites and between years.
For between year comparisons, we used data from the Institutes other
and ongoing work at Garibaldi Bluff and Rendezvous Bay.
Brittle stars (Ophiuroidea) increased between 1996 and 1997 at Little
Bay (figure 6.1) and at Garibaldi Bluff, but not at Rendezvous Bay. This
pattern is consistent with an increase in sediment at these sites, as brittle
stars live under rocks and coral rubble in soft substrates. At Little Bay,
jetty construction increased sediment load while at Garibaldi Bluff, volcanic
activity has increased the amount of soft sediments. There has been no change
in sediment input at Rendezvous Bay. Feather duster worms (Sabellidae) increased
at all sites suggesting that jetty construction is not a causal factor in
their increase. Feather duster worms are filter feeders, and their increase
coupled with an increase in planktivorous fish suggests that nutrient and
productivity levels around the island have increased. Whether this is due
to volcanic activity or other factors (e.g. the Orinoco Plume brining nutrient
rich water to the Antilles in December 1996) is unknown at this stage. Octopus
were observed to leave dens in Area A during the construction phase and
they did not return.
Other Observations: The marine environment was kept generally
free of garbage and waste materials during the construction phase from December
1996 to March 1997. L. G. Mouchel instituted a policy of not-dumping materials
in the sea and this was successful.
Training of Local Personnel: Many small islands lack local personnel
with the technical skills necessary for monitoring and management of their
natural resources (UNEP 1994; GCRMN 1996). A key component of this work
was the training of local personnel in coral reef monitoring and mitigation.
SEI scientists trained (and hired during the training process) Dwayne Cassell
and Patrick Laplace in monitoring techniques. The Institute sponsored Gerard
Gray (chief environment officer for Montserrat) to qualify as a SCUBA diver,
and subsequently trained him in reef monitoring, The Institute adapted its
manual "Ecology in Action: Coral Reef Monitoring , Answers to Frequently
Asked Questions" by Timothy Grubba specifically for this program,
and copies were presented to trainees and the National Trust. This training
provided Montserrat with local personnel (including a high-level civil servant
with responsibility for the environment) who are skilled in scientific monitoring
and with a general knowledge of coral reef ecology and species identification.
Prior to this training, marine ecological and monitoring skills did not
exist locally on the island.
Other: As a service to Montserrat, SEI independently developed
an educational snorkel trail in Little Bay. The trail was developed by SEI
biologist Alan Cooper. A map and description of the trail was provided to
local organizations, and government agencies.
Overall Conclusions
The EIA recommended the relocation of the jetty to a more southerly site
in Little Bay, and a new location was subsequently chosen. This was a wise
choice. The marine life close to the construction is now degraded from construction
activity and habitat destruction. The reefs and marine life from Area B-D
(westward along the bluff) remain healthy. Further, juvenile species have
recruited successfully to these areas (B-D), and juvenile lobster are still
common. The relocation of the jetty ensured the continued survival of the
coral reef ecosystem and ecological processes in Little Bay. Based on the
results from this monitoring and mitigation study, had the proposed original
location been adopted, the coral reefs over much of Rendezvous Bluff would
have perished, with important consequences for marine life and fisheries
at an island-wide level.
The EIA additionally recommended a new design that allowed for increased
water flow and was more stable and permanent. The new design has met many
of these requirements. However, we cannot fully evaluate its impacts in
this study as the jetty has not been fully completed.
Specific conclusions
Coral Transplants: The goal of the coral transplant project
was to prevent the mortality of corals close to the construction zone. The
results presented in this report illustrate that this goal was achieved.
At the time of writing, all transplanted corals were alive and feeding,
and fish had taken up residence on some coral heads. By contrast, corals
and other species close to the construction zone were bleached and buried
by sediment.
Monitoring Physical Factors: Impacts on Sediment and Water Clarity:
The goal of this component was to monitor changes in sedimentation and water
clarity, and to provide an early warning system in the case of serious damage
to the environment. Our results indicated increased sediment input from
the construction. Impacts were largely localized, as predicted. However,
when fine fill material was being used, impacts began to spread to a wider
area, and scientists observed a decrease in fish life. SEI scientists presented
the findings and concerns to Mr R. Trevitt of L. G. Mouchel and to Edgehill
Contractors. As a result action was taken to remedy the situation. In this
case, a new and coarser fill material was found. Fish life subsequently
rebounded.
Monitoring Changes in the Marine Life: The goal of this
component was to monitor changes in the marine life in Little Bay, and to
relate those changes to jetty construction. Based on the results of this
project and on other data from our ongoing studies, we were able to detect
and evaluate impacts from jetty construction and changes due to natural
phenomena. As predicted by the EIA, marine life close to the construction
was impacted, but impacts rarely extended beyond the immediate area (Area
A). Because of the short-term duration of this project, we cannot fully
evaluate the long-term changes due to jetty construction, particularly in
the central and eastern sections of Little Bay.
Key Outcomes
The monitoring and mitigation work provided valuable information for
managers and decision-makers, scientists and conservation groups. In this
project, we were able to document specific impacts of jetty construction
on the physical habitat (through changes in sedimentation and water clarity),
and learn how those changes affected marine life. This included identifying
which particular species are more susceptible to impacts and how some groups
(e.g. fish) respond to disturbance. The monitoring work provided important
information on the spatial extent of construction impacts on marine life
over the 3 month construction period.
As a result of the monitoring and mitigation work we learned that we
can provide an early-warning system for unacceptable levels of sedimentation,
and its impacts on marine life. In a climate of co-operation, changes can,
and in this case were made, to stop activities leading to unacceptable damage.
The results of the monitoring and mitigation work enabled an evaluation
of the recommendations and predictions of the EIA. This information is useful
for decision-makers in future policy and planning.
We learned that it was possible to prevent the mortality of key coral
species by transplanting them carefully to a new location.
The availability of original scientific data collected during other monitoring
and research studies proved invaluable in interpreting changes in the marine
life. For instance, it was possible to identify changes that could clearly
be attributed to construction, and also to identify changes that were occurring
on an island-wide basis and therefore unlikely to be due to construction.
Continued monitoring of coral reefs is essential.
Finally, the project showed that, with careful planning and work, it
is possible to meet the safety requirements for Montserrat, without bankrupting
the marine natural resource base. This project minimized damage to the marine
environment and ensured the conservation of fragile marine resources. This
was achieved through the collaborative and committed work of a diverse groups.
We hope that Montserrat and all parties involved in this project will continue
in similar framework on all future ventures.
A note on figures: The figures accompanying this document are
the main summary figures illustrating some of the results of this project.
More detailed figures can be found in the full report. In the figures on
Little Bay, data are presented from the "designated Areas (Areas A-D)"
For comparison, data are also presented from the EIA results. These columns
are labeled NC, N, and O. NC refers to the North-Central location identified
in the EIA, this is the site of the current construction and it is equivalent
to Area A; N refers to the North location further west, and O refers to
the westernmost edge and of Rendezvous Bluff (approximately Area D).
ACKNOWLEDGMENTS
Sustainable Ecosystems Institute thanks the individuals and organizations
that helped to make this project a success. Thanks to Richard Trevitt (consulting
engineer for L. G. Mouchel and Partners), to Edgehill and the workers at
the Little Bay construction site for assistance and co-operation during
the project, John Adam, Sarita Francis, Alan Gunne-Jones, Mike Emmanuel,
Bruce Farara, and Joel Osborne, Thanks also to the ODA, Department of Fisheries,
Physical Planning Unit, and the Montserrat National Trust.
Coral Reefs Homepage
Volcanic Impacts on Coral Reefs
in Montserrat
Snorkel Trail Little Bay Montserrat
Emergency Jetty in Montserrat
Underwater Video
St Barthelemy Marine Reserve
Volcano Homepage

|