Reducing Uncertainty and Risk
Peer Review of
the Potential Impact of Dredging and Disposal on
At-Risk
Salmonids in the Lower Columbia River Estuary,
March - August
2001
Sustainable Ecosystems Institute
0605 Taylor’s Ferry Rd.
Portland, OR 97219
503.246.5008
www.sei.org
A journey of a thousand miles must begin with a single step.
¾Lao Tzu
Background
In the late 1980’s, the Port
of Portland joined with other lower Columbia River ports to request that the US
Army Corps of Engineers (Corps) consider deepening the river’s navigation
channel. The request was based on the ports’ desire to remain competitive in an
industry where larger ships with deeper drafts were becoming the norm. The Port
of Portland, serving as the overall coordinator for the sponsoring ports, and
the Corps co-sponsored a feasibility study, which was completed in August 1999.
The study recommended deepening the channel an additional three feet along
103.5 miles of the Columbia River below Vancouver, Washington.
Earlier in the year,
Congress had authorized the project. Congressional appropriations, however,
could not be released without a green light ¾ or a “no-jeopardy Biological
Opinion” ¾ from the National Marine Fisheries Service (NMFS) and the US Fish
and Wildlife Service (FWS). Congress set a deadline of December 31, 1999, for
the two regulatory agencies to weigh in on their opinions. With just weeks to
the deadline, NMFS and FWS each issued the Corps separate no-jeopardy
Biological Opinions (BiOps) and each attached various conditions for the Corps
to meet over time, following completion of the channel deepening project.
Essentially, the two BiOps agreed with the Corps’ and the Port of Portland’s
Biological Assessment that the proposed channel deepening project would have no
significant impact on the region’s 22 federally listed fish and wildlife
species.
Less than two months later,
in February 2000, a coalition of environmental organizations filed a lawsuit to
block the proposed channel deepening project. The lawsuit asked a federal court
to set aside the no-jeopardy BiOps and to require a new opinion. The lawsuit
alleged the BiOps lacked scientific foundation and implied that the regulatory
agencies’ approval had more to do with meeting the reporting deadline (December
31, 1999) for congressional appropriations than with meeting agency BiOp
responsibilities.
That summer, in a surprising
reversal, NMFS withdrew its BiOp and requested a “reconsultation” with the
Corps. The two agencies, however, were unable to reach agreement, and by the
end of the year, negotiations had collapsed. To resolve the impasse, the principal
parties (Army Corps, Port of Portland, NMFS, and USFWS) agreed in January 2001
to retain the independent scientific peer review services of the Sustainable
Ecosystems Institute.
About the Sustainable Ecosystems Institute
In
1992, Dr. Deborah Brosnan founded the Sustainable Ecosystems Institute (SEI) to
give academic science a stronger voice in natural resource management, and to
encourage use of science-based, cooperative approaches to environmental problem
solving. The organization is a public-benefit, non-profit association of
scientists specializing in peer review, a time-honored process of independent
review or input from qualified individuals having no personal stake in the
outcome of a decision that concerns only the scientific validity of the
evidence and analyses underlying a proposed action or decision.
SEI
is committed to the use of impartial science of the highest standard. The
reputation of the group hinges upon maintaining neutrality and on building
consensus. An environmental consensus process is one in which all those who
have a stake in the outcome aim to reach agreement on outcomes that resolve or
advance issues related to environmental sustainability. Although participants
may not agree with all aspects of the agreement, consensus is reached if all
participants are willing to live with the total package. Consensus processes
are typically guided by ten principles outlined below.
Ten Principles for Building Consensus†
1. Purpose-driven: The parties have a common concern and a commitment to the process.
2. Inclusive: All stakeholders having a significant interest in the outcome are involved.
3. Voluntary participation: The parties who are affected or interested participate voluntarily.
4. Self-design: The parties design the consensus process.
5. Flexibility: The parties are open to changing the process as circumstances dictate.
6. Equal opportunity: The proceedings are transparent and information is widely accessible.
7. Respect for diversity: The parties have a mutual respect for diverse values and interests.
8. Accountability: Parties are accountable to their constituencies and to the process.
9. Time limits: The process is guided by a realistic set of deadlines and milestones.
10. Implementation: Parties are committed to implementation and effective monitoring.
† Cormick, Gerald, Norman Dale, Paul Edmond, S. Glenn Sigurdson, and Barry D. Stuart. 1996. Building consensus for a sustainable future: Putting principles into practice. National Round Table on the Environment and the Economy: Ottawa, Canada.
Fundamental Elements of A Successful Peer Review Process
There
are essentially six fundamental elements to a successful peer review process:
1) assessing the problem, 2) gathering
an expert team 3) designing the
process, 34) facilitating the process,
5) seeking commitments to implement agreements, and 6) evaluating success. Each
is described below in general terms, as well as in their relationship to the
Columbia River Channel Deepening project.
1. Assessing the Problem. SEI’s first task was to
conduct a conflict assessment ¾ the mediator’s method of determining the nature of the problem and the
commitment the principal parties have in finding common ground. The nature of
the problem is always more than what meets the eye. In the case of the Columbia
River Channel Deepening project, the problem on the surface was whether the
proposed action (channel deepening) posed a significant threat to listed
salmonids. But below the surface, the problems had to do with an erosion of
trust among the principal parties, stemming from the withdrawal of the
Biological Opinion and the subsequent failure of the parties to reach
resolution on a number of issues.
Dr.
Steven Courtney, SEI Vice President for Programs, served as the mediator. Dr.
Courtney assessed that much of the problem stemmed primarily from different
interpretations of the facts and that the solution would therefore lie in
getting a highly competent, impartial panel of scientists to review the facts
and thereby help resolve disputes. The process he proposed ¾?a series of science panel
meetings in which the parties laid out for review and discussion the facts as
they saw them ¾?would elevate the substantive issues (scientific facts) above the
emotional issues (distrust). With some level of commitment obtained from each
party, Dr. Courtney was then able to work with the principal parties to
identify the critical scientific and technical issues. These issues were
primarily those raised by NMFS and FWS in their withdrawal of the Biological
Opinion.
2. Gathering an Expert Team. A skilled
mediator is central to a successful peer review process. The mediator is the
architect of the peer review process, assessing the problem, working with
parties to design the process, facilitating the process through planning and
action, and seeking commitments from the parties to implement agreements. The
mediator is an independent person, acceptable to all the participants, whose
focus and expertise is in managing and shepherding the process and in assisting
disputing parties in finding common ground. In effect, the mediator is both a
‘process manager’ and a ‘dispute manager’. A skilled mediator:
Leads
by example, modeling the types of behavior expected from others.
Employs
active listening skills.
Shares
his or her personal thoughts and feelings as a barometer for groups.
Works
adroitly behind the scenes, resolving disputes and addressing complex technical
issues like scientific uncertainty.
Throughout the peer review
process, Dr. Courtney filled the critical role of interpreter/translator.
Uniquely he combined scientific expertise with an understanding of natural
resources policies and constraints. As such, he communicated between the
scientific and non-scientific constituents. This ability to move seamlessly
between two very different realms is fundamental to a successful scientific
peer review process. Not only was Dr. Courtney able to translate complex,
technical concepts into everyday language, but he was equally able to reframe
general questions from stakeholders in a manner that spoke directly to the
science panel’s specific charge. As a result, Dr. Courtney commanded the
respect of the science panel, project managers, stakeholders, and the media.
Due to the highly technical
and complex nature of this particular peer review, it was essential for Dr.
Courtney to be supported by a carefully selected team of experts. Operating
under a modest budget, Dr. Courtney decided the interests of his clients could
best be served by two support staff ¾one to serve as scientific liaison to the science
panel and the technical presenters, and the other to manage outreach to
stakeholders, media relations, and meeting logistics. Botanist Dr. Tatiana
Boyle with experience in sustainable conservation filled the role of science
manager; Wendy Hudson with several years experience in program management,
filled the role of project manager. All three SEI staff members worked closely
with the four agency project managers, and Dr. Courtney also periodically
conferred with some of the project managers’ supervisors or made presentations
on the progress of the SEI process to joint supervisor meetings.
3. Designing
the Process. There are essentially three fundamental elements to consider in
process design: 1) facilitating group
ownership of the process design, 2)
clarifying roles and responsibilities, and 3) establishing ground rules. Each
is described more fully below.
Facilitating
group ownership. The next step was to work in concert with the principal parties to
‘design’ the process. Parties tend to be more invested in a process and to
respect rules more when they have had a meaningful hand in shaping them.
Moreover, when problems arise later in the process, as they inevitably do, the
parties have an agreed-upon framework for resolving differences. While this
particular peer review model rested on the use of an independent, scientific
review panel, SEI nevertheless was able to give the principal parties a sense
of ownership in the process design.
Accordingly,
the parties recommended that the science panel be composed of seven respected
scientists with a range of expertise relevant to the project. To maintain its
standards of impartiality, SEI reserved the right to select panel members. The
principal parties were allowed to object to any SEI nominations, but not to
control the selection process. Only one objection was raised for which SEI
found an acceptable replacement. In concert with Dr. Courtney, the project
managers decided on six science panel meetings over the course of six months,
which SEI would organize. The six meetings would be open to the public and
would focus on major areas of concern raised in the withdrawal of the
Biological Opinion (e.g., sediments and sediment quality, toxic contamination
in fish). SEI would keep an audio and visual record of the meetings, and would
post relevant information (e.g., presentations, meeting summaries, etc.) on the
organization’s web site.
Clarifying
roles and responsibilities. Roles and responsibilities were clarified among project managers and
between project managers and SEI. Among project managers, the roles and
responsibilities entailed decisions around standards of conduct and behavior,
media relations, confidentiality, and information sharing. For example, the
principal parties agreed to an open sharing of information and to refer all
media inquiries to SEI. Roles and responsibilities also entailed respecting
each other’s values, knowledge, and institutional constraints. For example, the
constraints of the action agencies (Army Corps and the ports) are quite
different from those of the regulatory agencies (NMFS and FWS).
Between
the project managers and SEI, roles and responsibilities ran the gamut from
identifying necessary products and services to payment for services. For Dr.
Courtney, roles and responsibilities included impartiality, focus on technical
issues as opposed to policy issues, and strategic planning. For his staff, they
included technical assistance, public outreach, meeting logistics, and
record-keeping.
Establishing
ground rules.
Ground rules must be acceptable to all the principal parties, and generally
answer the familiar questions of who, why, what, how, where, and when. With
respect to the Columbia River Channel Deepening project, the answers to these
questions were:
Who (will be at the table): The principal parties consisted of four
project managers, one each from the Army Corps, NMFS, USFWS, and the Port of
Portland (representing the six ports along the lower Columbia River). The
parties understood that they were permitted to bring technical staff to any of
the meetings. Because so many federal agencies were involved in the dispute,
strong consensus existed to open the six panel meetings to the interested
public.
Why (goals): The principal parties reached common ground on the goal of
the process, which in essence was to determine whether a scientific basis
exists to attribute declines of threatened and endangered fish to effects of
the project.
What (issues and non-issues): The principal parties agreed to the focus
of the meetings ¾ the issues that would and would not be addressed. In this
case, the agreement was on a range of concerns (raised by NMFS in its
withdrawal of the Biological Opinion) as they potentially relate to effects of
the channel deepening. Further, the parties agreed to a presentation format in
which technical staff would present the best available information for a
particular topic and respond to questions from the panel and audience.
How (rules of procedure): This concerns roles and responsibilities
toward each other, the mediator, and external parties such as the media. The
focus is on good-faith efforts resulting in a win-win situation as opposed to
positional bargaining resulting in a win-lose scenario. These are most
effective when designed by the principal parties and written down. In the case
of media relations, for example, the principal parties agreed to refer all
inquiries to SEI.
Where and when (logistics and schedule): The principal parties charged
SEI with finding a suitable neutral location that could accommodate up to 75
people. Meetings occurred monthly. In addition, SEI staff met regularly with
the project managers prior to each meeting to set goals and objectives and to
review other relevant information. SEI maintained a database of approximately 150
interested parties and informed them regularly of upcoming meetings.
4.
Facilitating the Process. As important as the mediator is to designing the
process, so is he or she to facilitating the process. In particular, the
mediator plays a crucial role in resolving problems, which invariably arise
throughout the course of the process. Because the resolution of disputes can be
so time-consuming, it is important that the mediator be supported by a
competent team to address the myriad details that go into facilitating the
process. In the case of the Columbia River Channel Deepening project, the SEI
team was instrumental in coordinating the science panel, organizing the six
meetings, and conducting outreach and media relations.
Resolving
Problems.
The attainment of solid, shared understandings is essential, particularly
during the early and often sensitive stages of trust-building and negotiation.
However, while it is important to clarify roles and responsibilities and to
establish ground rules at the outset, it is equally important to maintain
flexibility throughout the design process and the peer review proceedings. It
is virtually impossible to anticipate every possible development in a peer
review or consensus process. By designing flexibility into the process,
participants can anticipate and better handle changes or surprises when
confronted with them.
As
a peer review process unfolds, common understandings and decisions reached at
the outset of the process can begin to unravel. In the Columbia River Channel
Dredging project, for example, the following initial understandings were
challenged later in the process:
Changes in
priority:
Initially the issue of salinity intrusion into the lower estuary as a result of
the dredging was considered by many to be a priority concern. During the course
of the proceedings, however, the science panel saw no ‘clear and present
danger’ with regard to the impacts of sediment and sediment quality on fish.
The panel determined that sediments appear to have little risk, although some
uncertainty remains. Therefore, the panel viewed them as a second-order
monitoring priority.
Broadened
issues: The
physical modeling used by the Corps in the original Environmental Impact
Statement modeled the potential effects of the project on river flow. The
science panel expressed concern that the modeling focused largely on
intermediate flow ranges without considering extreme low-flow conditions as
were currently being experienced in the region-wide drought. SEI then tasked
the Corps with determining the feasibility of conducting additional modeling on
this issue within the short timeframe remaining in the SEI process. The Corps
agreed to contract for additional modeling and to have results ready for the
final panel meeting.
Disputes over
‘facts’:
Midway through the peer review process, NMFS scientists presented ‘new
information’ on the effects of toxic contaminants on fish. While this
revelation caused some discomfort among the regulatory agencies (mostly in
terms of how the information was revealed), the science panel found the
information to be largely speculative and without rigorous empirical evidence.
More time
needed to complete tasks and reach agreement: The initial process design, agreed to by
all parties, called for a penultimate meeting on monitoring and adaptive
management. However, as the meeting date drew closer, the principal parties
decided they were not yet prepared to address these issues. By arranging a
closed session between project managers, SEI staff, and some of the panel
members, SEI was able to help the parties through complex negotiations, and
ultimately, to commit to a monitoring and adaptive management program.
Impasse and
doubts about the feasibility of resolution: On more than one occasion, SEI was faced
with the very real possibility that the entire process would collapse due to
the occasional contentiousness of one or more of the parties. These impasses
required Dr. Courtney to play a skillful, behind-the-scenes balancing act with
each of the project managers. It required him to remind the parties of the
importance of having flexible attitudes and creative approaches to
problem-solving. It also required Dr. Courtney to be similarly flexible.
Coordinating
the Science Panel. The scientific credibility of the science panel is paramount in a
peer review process. This is the independent group of scientists that digests
highly technical and complex information and renders an impartial opinion on
its merit. It is essential that panelists be of sufficient stature to command
the respect of the principal parties, as well as of the public and media.
Dr.
Tatiana Boyle was responsible for recruiting the seven members of the SEI
science panel and for all interactions with them. In preparation for each
meeting, she compiled review literature recommended by the project managers, as
well as copies of technical presentations. In addition, she took care of all
the logistical details related to the panel, such as ground transportation,
hotel accommodations, breakfast meetings, dinner socials, honoraria payments,
and expense reimbursements. Finally, Dr. Boyle ensured that all presentations
were posted on the SEI web site.
At
the June meeting, the project managers expressed frustration with a perceived
lack of direction from the panel. Panelists were quick to point out that their
charge was not to guide, but to review and evaluate the material presented to
them. The onus, therefore, rested with the project managers to know what
questions they wanted to have answered and to have the panel’s response to
those questions on record. To mitigate the sense of frustration experienced by
both project managers and panelists, the SEI team worked with the project
managers to develop a questionnaire for the science panel to complete before
the July meeting. Dr. Boyle worked with the panel to meet the tight deadline,
tabulated panel responses, contacted individual panelists to clarify some of
their responses, and wrote a brief summary of the panel’s collective responses.
Organizing
the Meetings.
The location of meetings and the quality of meeting facilities and services
play an important role in the overall success of a peer review process. The
Columbia River Channel Deepening project was fortunate to be able to conduct
most of its meetings on the Vancouver, Washington, campus of Washington State
University. The facilities were free and campus staff were very supportive of
the SEI process. The closed July meeting was held at the Port of Portland, and
the final public meeting at the Downtown Marriott Hotel in Portland.
Wendy
Hudson handled all meeting logistics. Specifically, she was responsible siting
the meetings and arranging for food and beverage service and other logistical
details. She recorded all meetings and afterwards transcribed the discussions
between panelists and presenters. She arranged to have transcriptions (“Meeting
Minutes”) and meeting summaries posted on the SEI web site, along with other
meeting information, such as the meeting agenda and a list of attendees. Ms.
Hudson also prepared materials for interim planning sessions with the project
managers.
Conducting
Public Outreach and Media Relations. Attention to relations with stakeholders and the
media cannot be underestimated. These groups have legitimate concerns and the
expectation that they will be heard. Anything short of making a good-faith
effort to meet their needs can have significant consequences for a peer review
process.
Ms.
Hudson served as the public point of contact for the project, answering
questions from the public and the media. She maintained a database of
approximately 150 “interested parties” and sent them regular email
announcements about upcoming meetings. For the press, she developed press
releases and press packets, and occasionally fielded their calls for more
information.
5. Seeking Commitments to Implement Agreements
No
peer review process is complete without a commitment from the principal parties
to implement agreements. Although a peer review process is not typically
characterized by formal agreements, this particular process, with its attention
to risk and uncertainty, strongly suggested a need for monitoring and adaptive
management. Consequently, SEI staff reacted quickly when the project managers
cancelled the July meeting on monitoring and adaptive management.
The
specifics of the two issues had been a source of disagreement between the
action and regulatory agencies, and Dr. Courtney felt it imperative that the
principal parties have the opportunity to air their concerns in a safe
environment. The closed July meeting provided just such an environment. SEI
staff arranged for three of the science panelists to discuss with the project
managers broad concepts related to monitoring and adaptive management, which
created the comfort-level needed by the project managers to speak candidly.
Following
the July meeting, Dr. Courtney worked behind the scenes with individual project
managers to secure their commitment to a flexible monitoring and adaptive
management program. Although details remained to be negotiated, Dr. Courtney
did place project managers on record in the final peer review meeting regarding
agency pledges to implement a monitoring and adaptive management program with a
minimum duration of five years.
6. Evaluating
Success.
Science is rarely able to provide finality on issues. In the absence of
certainty, though, science offers the best possible shared ‘theory’ about
relevant facts. Recognition of the limitations of science as a decision-making
tool, however, should not discourage the integration of science into
decision-making processes. Rather, environmental decision making demands that
decision makers remain open to new information, which is bound to keep changing
during and well beyond the end of a peer review process. Therefore, in terms of
evaluating the success of a peer review process, it is important not to focus
on whether the science is ‘right’ or ‘wrong’, but on whether it provides a
sufficient basis for decision-making, factoring in degrees of risk and
uncertainty.
By the final science panel meeting in August 2001, the SEI peer review
process revealed an insufficient scientific basis to attribute declines of
threatened and endangered fish to effects of the proposed channel deepening.
Perhaps more importantly, the SEI science panel process successfully achieved a
commitment from all parties to participate in the joint development and
implementation of a scientifically rigorous monitoring and adaptive management
program. At this writing, the ports and the Corps are preparing a new Biological
Assessment (BA) that will address many of the issues raised throughout the peer
review process, as well as address the structure of a monitoring and adaptive
management program.
SEI has a standard evaluation form it sends to panelists and clients (in
this case, the project managers) following every peer review process. Responses
to these forms help SEI improve its format for future processes.
* * *